Shutter Replacement Update 6

March 11, 2015

Dear Regency Residents,

 

After the required safety paperwork was signed off & handed to Expert Mike this morning, the safety lines were installed, and after they too were inspected, the removal of shutters began on B-1 06 stack.  Removal began at 11AM. 


Building #1 - Today the crew removed 306, 406, 506, and 606 shutters.  Tomorrow, at 8AM they will be able to begin removing at 706 working up the stack.   With the weather cooperating, they should complete the entire 06 stack removal in preparation for JB Painter on Thursday.

 

Building #2 - 8AM Thursday, shutter removal will begin at LN6 and the crew will work up the stack removing shutters.  Be certain all items are off of your balcony.   

 

Thank you for your patience during this project.

 

Sincerely,

Pat

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic