Shutter Replacement Update #7

March 11, 2015

FOR YOUR SAFETY - 04, 05, 06 - BALCONY ON EAST SIDE IS CLOSED AND ALL ITEMS MUST BE REMOVED.

 

Building #1: 

~~06 stack hurricane shutter removal complete at 2:45PM. 

~~JB Paint will begin cleaning, priming & painting 06 tomorrow morning.

~~05 stack shutter removal begins tomorrow at 8:AM

 

Building #2:

~~06 stack removal complete LN through 3rd floor as of this writing (3:15PM).  The crew is working on removing 406 shutters.

 

Both Buildings tomorrow:

Removal of 05 shutters will be worked on in both buildings tomorrow.

 

Pat

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic