Shutter Replacement Update #8

March 12, 2015

Building #1:

06 stack 

~~~shutter removal complete

~~~JB Paint pressure washed and patched stucco on 8 balconies

~~~Friday, JB will begin painting on PH and work down

05 stack 

~~~3.5 sets removed

 

Building #2:

06 stack

~~~shutter removal complete from LN up to and including 906

~~~complete removal expected prior to noon Friday

~~~JB may begin pressure washing as early as Friday afternoon

05 stack

~~~LN removed and most of 305 removed

 

 

New shutters for B-1 06 are on site; several have been placed on 06 balconies.

 

PVC has been placed into the 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony.  Staff will be addressing the 05 slider PVC tomorrow.

 

Walt is assigned to Building #1 and Randy is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project.

 

Sincerely,

Pat

 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic