Shutter Replacement Update #8

Building #1:

06 stack

~~~shutter removal complete

~~~JB Paint pressure washed and patched stucco on 8 balconies

~~~Friday, JB will begin painting on PH and work down

05 stack

~~~3.5 sets removed

Building #2:

06 stack

~~~shutter removal complete from LN up to and including 906

~~~complete removal expected prior to noon Friday

~~~JB may begin pressure washing as early as Friday afternoon

05 stack

~~~LN removed and most of 305 removed

New shutters for B-1 06 are on site; several have been placed on 06 balconies.

PVC has been placed into the 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. Staff will be addressing the 05 slider PVC tomorrow.

Walt is assigned to Building #1 and Randy is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project.

Sincerely,

Pat