Shutter Replacement Update #9

Building #1:

06 stack

~~~shutter removal complete

~~~JB Paint pressure washed and patched stucco on all 06 balconies

~~~JB began painting on PH and completed 8 balconies

~~~JB will begin painting at 506 Monday

05 stack

~~~Expert removed shutters from LN through 805 inclusive

~~~Expert will begin removing shutters at 905 on Monday

Building #2:

06 stack

~~~shutter removal complete

~~~JB will begin pressure washing at PH level late Monday morning

05 stack

~~~Expert removed shutters from LN through 605 inclusive

~~~Expert will begin removing shutters at 705 on Monday

All 04 units must have items removed from the east side balcony.

PVC has been placed into all 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. Staff will begin installing PVC in the 04 sliders on Monday, March 16th.

Walt is assigned to Building #1 and Randy is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project.

If you notice anything which warrants attention after hours, please call Security ASAP.

Sincerely,

Pat


Featured Posts
Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us
No tags yet.
Search By Tags

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic