Shutter Update # 11

Building #1:

06 stack

~~~shutter removal complete

~~~shutters placed - all floors

~~~JB painting complete

~~~inspection scheduled tomorrow

05 stack

~~~all shutters removed

04 stack

~~~measured LN - PH

~~~shutter removal scheduled to begin on Wednesday, March 18th

Building #2:

06 stack

~~~JB painting starting tomorrow at PH

~~~shutter removal complete

~~~JB stucco patching complete

~~~JB pressure washing complete

05 stack

~~~shutters removed LN through 905 inclusive

~~~removal of 1005 through PH delayed today

~~~rescheduled for tomorrow after inspection

04 stack

~~~measured LN - PH

~~~shutter removal possibly Wednesday

PVC has been placed into all 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony.

Walt is assigned to Building #1 and Randy is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project.

If you notice anything which warrants attention after hours, please call Security ASAP.