Shutter Update #13

March 19, 2015

Building #1:

06 stack  

~~~LN shutter installation started

05 stack 

~~~all shutters removed

~~~inspected all areas on balconies from PH down to LN. 

~~~JB pressure washing complete

~~~JB scraping and patching Friday 

04 stack

~~~measured LN - PH complete

~~~shutter removal started LN through 3

 

 

Building #2:

06 stack

~~~JB painting complete

~~~shutter removal complete   

~~~JB stucco patching complete

~~~JB pressure washing complete

~~~inspection of every balcony delayed until Friday

05 stack

~~~shutters removed LN through 1205

~~~PH will be removed Friday due to load of shutters rec'd today

~~~inspection of every balcony delayed until Friday

04 stack

~~~measured LN - PH

~~~shutters removed on floors LN and 3

 

PVC has been placed into all 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

Walt is assigned to Building #1 and Randy is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project.

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic