Shutter Update # 14

March 20, 2015

All items on the 03 balconies should be removed as work has started in the 04 stack.

 

For safety reasons no one is permitted on east side balconies in the 06, 05, 04, 03 stacks during work days, 8:AM - 4:30PM.

 

Building #1:

06 stack  

~~~LN shutter installation completed

05 stack 

~~~all shutters removed

~~~inspected caulked penetrations on balconies from PH down to LN 

~~~JB pressure washing complete

~~~JB scraping, stucco patch complete from PH down to 3 

~~~inspection will be scheduled for the beginning of the week

04 stack

~~~measured LN - PH complete

~~~shutters removed LN through 5th floor

 

 

Building #2:

06 stack

~~~JB painting complete

~~~shutter removal complete   

~~~JB stucco patching complete

~~~JB pressure washing complete

~~~caulking of every penetration on every balcony was inspected by myself and the engineer 

05 stack

~~~all shutters removed

~~~caulked from PH down to and including 9th floor

~~~inspection of every balcony delayed until the beginning of the week

04 stack

~~~measured LN - PH

~~~shutters removed on floors LN and 3

 

PVC has been placed into all 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project.

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic