Shutter update #15

All items on the 03 balconies should be removed as work has started in the 04 stack.

For safety reasons no one is permitted on east side balconies in the 06, 05, 04, 03 stacks during work days, 8:AM - 4:30PM.

Definitions

Taken down: This means when shutter blades & tracks are no longer installed on your balcony.

Removed: This means when old shutters are taken off of your balcony.

NOTE: Old shutters will be removed from each balcony when new shutters are placed for installation.

Building #1:

06 stack

~~~LN shutter installation completed

~~~306 shutters installed

~~~PH6 shutter installation began / weather prevented completion

~~~all new shutters have been placed on balcony areas

05 stack

~~~all shutters have been taken down

~~~inspected caulked penetrations on balconies from PH down to LN

~~~JB pressure washing complete

~~~JB scraping, stucco patch complete

~~~paint complete from PH - 9 inclusive

04 stack

~~~shutters taken down LN through 7th floor

Building #2:

06 stack

~~~LN shutter installation began

~~~delivered new shutters to all balconies

~~~removed all old shutters from balconies

05 stack

~~~all shutters taken down

~~~caulking complete & inspected

04 stack

~~~shutters on LN and 3 have been taken down

PVC has been placed into all 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony.

NOTE CHANGE: Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project.

If you notice anything which warrants attention after hours, please call Security ASAP.