Shutter Update #22

April 2, 2015

Thursday, April 2nd, project work will end at 4:30PM and resume Monday, April 6th at 8:AM.

 

Due to the fact there will not be construction work going on during the extended Easter Weekend, it is safe for you to enjoy your balcony.  If old shutters are stacked, be careful of sharp edges and do not permit unsupervised children access to the area.

BEFORE 8AM Monday, April 6th, please remove any personal items from the east balcony area.

 

For safety reasons no one is permitted on east side balconies in the 06, 05, 04, 03, and 02 stacks during work days, 8:AM  - 4:30PM. 

 

All items on the 02 balconies must be removed as work has begun on the 03 stack.  Residents in the 02 stack must stay off their balcony between 8:AM - 4:30PM.    If you need assistance moving balcony items, please phone the office for  assistance.

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.

 

NOTE: Old shutters will be removed from each balcony when new shutters are placed for installation.

 

Building #1:

06 stack  

~~~PH6 shutters installation complete

~~~1206 shutter installation complete

~~~1106 shutter installation complete

~~~1006 shutter installation complete

~~~906 shutter installation complete

~~~806 shutter installation complete

~~~706 shutter installation complete

~~~306 shutter installation complete

~~~LN shutter installation complete

~~~old shutters have been removed and new shutters have been placed on each balcony

05 stack 

~~~PH5 80% complete

~~~305 shutter installation complete  

~~~LN5 shutter installation complete

~~~new shutters have been placed and old shutters removed LN - PH

~~~JB completed painting

04 stack

~~~JB starts scope of their work tomorrow which is pressure washing,

        followed by patch / stucco repair 

~~~caulking inspection PH-LN complete

~~~LN - PH shutter take down complete / relocated away from slider

03 stack

~~~LN old shutters taken down

~~~303 old shutters taken down

~~~403 old shutters taken down

~~~503 old shutters taken down

~~~603 old shutters taken down

 

Building #2:

06 stack

~~~PH6 shutter installation complete

~~~1206 shutter installation complete

~~~1106 shutter installation complete

~~~1006 shutter installation complete

~~~306 shutter installation complete

~~~LN shutter installation complete

~~~new shutters are placed and old shutters removed from all balconies

05 stack

~~~all shutters taken down

~~~old removed & new shutters placed on LN - 07 inclusive

~~~caulking complete & inspected

~~~JB painting, scope of work complete including pressure washing

        & patch / stucco repair 

04 stack

~~~LN - PH shutter take down complete / relocated away from sliders

~~~caulking inspection complete

~~~JB painting, scope of work complete including pressure washing,

        & patch / stucco repair 

03 stack

~~~LN taken down

~~~303 taken down

~~~403 taken down

~~~503  taken down

~~~603  taken down

~~~703 taken down

 

PVC has been placed into all 03 and all 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project.

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic