Shutter Update #25

April 7, 2015

For safety reasons no one is permitted on east side balconies in the 06, 05, 04, 03, and 02 stacks during work days, 8:AM  - 4:30PM. 

 

All items on the 02 balconies must be removed as work has begun on the 03 stack.  PVC is being placed in slider tracks to remind Residents in the 02 stack to stay off their balcony between 8:AM - 4:30PM.    If you need assistance moving balcony items, please phone the office for  assistance.

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.

 

NOTE: Old shutters will be removed from each balcony when new shutters are placed for installation.

 

ESS & RID inspections are done prior to phoning SLC for Final Inspection. 

April 6, 2014 ESS & RID inspected most units in Bldg 1 06.  The inspection included closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

 

St Lucie County has been contacted to schedule the Final Inspection on all remaining Building #1 06 stack units.

 

Building #1:

06 stack  - SLC FINAL INSPECTION will be completed on this stack by the end of the week.

~~~PH6 shutters installation complete / inspected by ESS & RID

~~~1206 shutter installation complete / inspected by ESS & RID

~~~1106 shutter installation complete / inspected by ESS & RID

~~~1006 shutter installation complete / inspected by ESS & RID

~~~906 shutter installation complete / SLC Final Inspection complete 2015.4.3

~~~806 shutter installation complete / SLC Final Inspection complete 2015.4.3

~~~706 shutter installation complete / inspected by ESS & RID

~~~606 shutter installation complete / inspected by ESS & RID

~~~506 shutter installation complete / SLC Final Inspection complete 2015.4.7

~~~406 shutter installation complete

~~~306 shutter installation complete / inspected by ESS & RID

~~~LN shutter installation complete / SLC Final Inspection complete 2015.4.3

05 stack 

~~~PH5 shutter installation complete

~~~1205 shutter installation complete

~~~1105 shutter installation complete

~~~1005 started

~~~305 shutter installation complete  

~~~LN5 shutter installation complete

~~~LN - PH new shutters have been placed and old shutters removed

~~~JB completed painting

04 stack

~~~PH4 - LN4 inclusive JB pressure washed, patch / stucco repair complete

~~~PH4 JB begins painting working down the stack

~~~ PH-LN caulking inspection complete

~~~LN - PH shutter take down complete / relocated away from slider

03 stack

~~~503 JB pressure washed, patch / stucco repair

~~~403 JB pressure washed, patch / stucco repair

~~~303 JB pressure washed, patch / stucco repair

~~~LN JB pressure washed, patch / stucco repair

 

Building #2:

06 stack

~~~PH6 shutter installation complete

~~~1206 shutter installation complete

~~~1106 shutter installation complete

~~~1006 shutter installation complete

~~~906 shutter installation complete

~~~806 shutter installation complete

~~~706 shutter installation complete

~~~606 shutter installation 90% complete

~~~506 shutter installation started

~~~406 shutter installation 40% complete

~~~306 shutter installation complete

~~~LN6 shutter installation complete

 

05 stack

~~~LN5 - PH5 inclusive - all shutters taken down

~~~LN5 through 1105 & PH new shutters placed on each balcony 

~~~caulking complete & inspected

~~~JB painting, scope of work complete including pressure washing

        & patch / stucco repair 

04 stack

~~~LN4 - PH4 shutter take down complete / relocated away from sliders

~~~caulking inspection complete

~~~JB painting, scope of work complete including pressure washing,

        & patch / stucco repair 

03 stack

~~~LN3 taken down

~~~303 taken down

~~~403 taken down

~~~503  taken down

~~~603  taken down

~~~703 taken down

~~~803 taken down

~~~903 taken down

~~~1003 taken down

~~~1103 taken down

~~~1203 taken down

 

PVC has been placed into all 03 and all 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project. 

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic