Shutter Update #29

April 13, 2015

For safety reasons no one is permitted on east side balconies in the 06, 05, 04, 03, and 02 stacks during work days, 8:AM  - 4:30PM. 

 

02 shutter removal began today.  There should be NO items on the balcony areas in that stack. 

 

PVC has been placed in slider tracks to remind Residents in the 02 stack to stay off their balcony between 8:AM - 4:30PM.    If you need assistance moving balcony items, please phone the office for  assistance.

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.  Old shutters will be removed from each balcony when new shutters are placed for installation.

 

ESS & RID inspections are done prior to phoning SLC for Final Inspection.  ESS & RID inspected all shutter installations in Bldg 1 and Bldg 2 / 06 stacks. Inspections included closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

 

Building #1:

06 stack 

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack 

~~~PH5 shutter installation complete

~~~1205 shutter installation complete

~~~1105 shutter installation complete

~~~1005 shutter installation complete

~~~905 shutter installation complete

~~~805 shutter installation complete

~~~705 shutter installation complete

~~~605 shutter installation started

~~~305 shutter installation complete  

~~~LN5 shutter installation complete

04 stack - April 13th & 14th, remove old shutters / place new on balcony

~~~PH4 - LN4 inclusive JB pressure washed, patch / stucco repair complete

~~~PH - LN JB painting complete

~~~PH - LN caulking inspection complete

~~~LN - PH shutter take down complete

~~~LN - 604 old shutter removed / new shutters placed

03 stack

~~~caulking inspection RID & ESS

~~~LN - PH inclusive taken down  

~~~503 JB pressure washed, patch / stucco repair

~~~403 JB pressure washed, patch / stucco repair

~~~303 JB pressure washed, patch / stucco repair

~~~LN JB pressure washed, patch / stucco repair

02 stack

~~~LN shutter take down started

 

Building #2:

06 stack

~~~County inspection started

~~~RID & ESS Final Inspection Thursday, April 9th 

NOTE:  The inspection included closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

05 stack

~~~PH5 shutter installation complete

~~~1205 pending tile replacement

~~~1105 shutter installation 95% complete

~~~LN5 through 1105 & PH new shutters placed on each balcony 

~~~JB painting, scope of work complete including pressure washing

        & patch / stucco repair 

04 stack

~~~704 shutter installation complete

~~~LN - PH inclusive shutters taken down 

~~~LN - PH old shutters removed; new shutters placed 

03 stack

~~~LN3 - PH3 inclusive taken down

~~~PH - LN  pressure washing complete

~~~PH - LN stucco scraped & patched  

~~~caulking inspection was April 9th

 

PVC has been placed into all 02, 03, 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project. 

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic