Shutter Update #32

April 16, 2015

01 UNITS - MONDAY, April 20th, Safway will install rigging on all 01 units.  Door hangers are on the entry doors to all 01 units in both buildings to remove all east side balcony items and to stay off of the balcony between 8AM - 4:30PM Monday through Friday. 

 

06 UNITS - MONDAY, April 20th the rigging will be removed from in front of your east side balcony, so please be certain no one is on that balcony during this time. 

~~~Bldg #1 - After Monday's equipment relocation, you will be able to use your balcony as the work will be complete on the 05 stack

~~~Bldg #2 - Although your shutter installation is complete, please stay off of your balcony from 8:AM - 4:30PM while ESS is installing on Bldg #2's 05 stack. 

  

RID / ESS Bldg 1 05 STACK FINAL INSPECTION - Friday, April 18th, ESS & RID will do a final inspection on Building #1 05 stack.  ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

 

SLC FINAL INSPECTIONS - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time.  These inspections are scheduled after the RID / ESS Final  Inspections.  If you are in residence, you will be notified of the date the inspector and I will be at your unit.

 

For safety reasons no one is permitted on east side balconies in the 06, 05, 04, 03, and 02 stacks during work days, 8:AM  - 4:30PM. 

 

PVC has been placed in slider tracks to remind Residents in the 02 stack to stay off their balcony between 8:AM - 4:30PM.    If you need assistance moving balcony items, please phone the office for  assistance.

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.  Old shutters will be removed from each balcony when new shutters are placed for installation.

 

Building #1:

06 stack 

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack  - RID / ESS inspection Friday, April 18th.

~~~PH5 shutter installation complete

~~~1205 shutter installation complete

~~~1105 shutter installation complete

~~~1005 shutter installation complete

~~~905 shutter installation complete

~~~805 shutter installation complete

~~~705 shutter installation complete

~~~605 shutter installation complete

~~~505 shutter installation complete

~~~405 shutter installation complete

~~~305 shutter installation complete  

~~~LN5 shutter installation complete

04 stack

~~~LN shutter installation started

~~~LN - 604 old shutters removed / new shutters placed

~~~804 - PH old shutters removed / new shutters placed

03 stack

~~~caulking inspection RID & ESS

~~~LN - PH inclusive taken down & pressure washed  

~~~PH - 7 inclusive, JB patch & stucco work complete

~~~PH - 9 inclusive JB paint complete

~~~503 JB pressure washed, patch / stucco repair

~~~403 JB pressure washed, patch / stucco repair

~~~303 JB pressure washed, patch / stucco repair

~~~LN JB pressure washed, patch / stucco repair

~~~PH - 703 painting complete

02 stack

~~~LN shutters taken down

~~~302 shutters taken down

~~~402 shutters taken down

~~~502 shutters taken down

~~~602 shutters taken down

 

Building #2:

06 stack

~~~SLC FINAL INSPECTIONS - several complete

05 stack

~~~PH5 shutter installation complete

~~~1205 pending tile replacement

~~~1105 shutter installation complete

~~~1005 shutter installation complete

~~~905 shutter installation  complete

~~~805 shutter installation 30% complete

~~~LN5 through 1105 & PH new shutters placed on each balcony 

04 stack

~~~704 shutter installation complete

~~~604 shutter installation complete

~~~504 shutter installation 50% complete

~~~LN - PH inclusive shutters taken down 

~~~LN - PH old shutters removed; new shutters placed 

03 stack

~~~LN3 - PH3 inclusive taken down

~~~PH - LN  pressure washing complete

~~~PH - LN stucco scraped & patched

~~~PH - LN painting complete  

~~~caulking inspection was April 9th

 

PVC has been placed into all 02, 03, 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project. 

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic