Shutter Update # 38

April 24, 2015

01 UNIT RESIDENTS - If you are leaving for an extended period, please remove all east side balcony items.  

~~~Bldg #1 - Take down of old shutters on your east balcony will begin the week of April 27th.  Work is presently being done on the 02 stack so please keep off of the east side balcony between 8AM - 4:30PM Monday through Friday. 

~~~Bldg #2 - When work begins on the 02 stack, you will be notified to keep off of your east side balcony. 

 

06 UNIT RESIDENTS - Rigging was removed from in front of your east side balcony.

~~~Bldg #1 - You may now place items back onto your 06 east side balcony as the 05 stack is complete. 

~~~Bldg #2 - Although your shutter installation is complete, please stay off of your balcony from 8:AM - 4:30PM while ESS is installing on Bldg #2's 05 stack.  It is near completion.

  

RID / ESS Bldg 1 05 STACK FINAL INSPECTION COMPLETE - Friday, April 18th, ESS & RID completed the final inspection on Building #1 05 stack.  ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

 

SLC FINAL INSPECTIONS - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time.  The inspections are scheduled after the RID / ESS Final Inspections and will begin the week of April 27th.  If you are in residence, you will be notified of the date the inspector and Regency Staff will inspect your shutters. 

 

PVC has been placed in slider tracks to remind Residents in the 01 & 02 stack to stay off their balcony between 8:AM - 4:30PM.    If you need assistance moving balcony items, please phone the office for  assistance.

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.  Old shutters will be removed from each balcony when new shutters are placed for installation.

 

Building #1:

06 stack 

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack  

~~~PH5 - LN5 - RID / ESS inspection Friday, April 18th / complete

04 stack

~~~PH4 shutter installation complete

~~~1204 shutter installation complete

~~~1104/03 pending tile replacement / demo 50%

~~~1004 shutter installation started / tile repair in center of balcony not at edge

~~~904 shutter installation complete

~~~804 shutter installation complete

~~~704 pending tile replacement / 80% complete

~~~604 shutter installation complete

~~~504 shutter installation 99% complete

~~~404 shutter installation 50% complete 

~~~304 Shutter installation 60% complete

~~~LN4 shutter installation  complete

03 stack 

~~~LN - 1003 / 1203 - PH old shutters removed / new shutters placed

~~~PH -LN  inclusive, JB patch & stucco work complete

~~~PH - LN inclusive JB paint complete

02 stack

~~~PH - LN caulking inspection of every balcony complete April 24th

~~~702 tile trough needs to be filled in.  JB will address week of April 27th.

 

Building #2:

06 stack

~~~SLC FINAL INSPECTIONS - several complete

05 stack

~~~PH5 shutter installation complete

~~~1205 pending tile replacement / awaiting tile

~~~1105 shutter installation complete

~~~1005 shutter installation complete

~~~905 shutter installation complete

~~~805 shutter installation complete

~~~705 shutter installation complete

~~~605 shutter installation complete

~~~505 shutter installation complete

~~~405 shutter installation complete

~~~305 shutter installation 60% complete

~~~LN5 shutter installation 60% complete

04 stack

~~~PH4 shutter installation complete

~~~1204 shutter installation complete

~~~1104 shutter installation  complete

~~~1004 shutter installation complete

~~~904 shutter installation complete

~~~804 shutter installation complete

~~~704 shutter installation complete

~~~604 shutter installation complete

~~~504 shutter installation  complete

~~~404 shutter installation complete

~~~304 shutter installation 75% complete

~~~LN - PH old shutters removed; new shutters placed 

03 stack

~~~LN - PH3 old shutters removed / new shutters placed

 

PVC has been placed into all 01, 02, 03, 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project. 

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic