Shutter Update #43

May 1, 2015

PLEASE DO NOT PLACE ITEMS ONTO YOUR EAST SIDE BALCONY IF YOU HAVE NOT RECEIVED A NOTICE THAT YOUR SHUTTER INSTALLATION AND ALL RELATED WORK IS COMPLETE. 

 

THE 04 STACK IN BUILDING 1 IS BEING PRESSURE WASHED THE WEEK OF MAY 4TH.

 

RID / ESS FINAL INSPECTION    

ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness.

 

01 UNIT RESIDENTS

~~~Bldg #1 - Take down of old shutters on your east balcony will begin the week of May 4th.  Work is presently being done on the 02 stack so please keep off of the east side balcony between 8AM - 4:30PM Monday through Friday. 

~~~Bldg #2 - Work has started on the 02 stack, so please keep off of your east side balcony between 8:AM - 4:30PM Monday - Friday. 

 

06 UNIT RESIDENTS 

~~~Bldg #1 - You may now place items back onto your 06 east side balcony as the 05 stack is complete. 

~~~Bldg #2 - You may now place items back on your 06 east side balcony as the 05 stack is nearly complete.  1205's tile installation is 99% complete today, May 1st, and shutter installation will follow the week of May 4th.  After completion of 1205's shutter installation, you will be advised via the Update that it will be safe to use your balcony. 

   

SLC FINAL INSPECTIONS - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time.  The inspections are scheduled after the RID / ESS Final Inspections and will begin the week of May 4th.  If you are in residence, you will be notified of the date the inspector and Regency Staff will inspect your shutters. 

 

PVC has been placed in slider tracks to remind Residents in the 01 & 02 stack to stay off their balcony between 8:AM - 4:30PM.    If you need assistance moving balcony items, please phone the office for  assistance.

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.  Old shutters will be removed from each balcony when new shutters are placed for installation.

 

Building #1:

06 stack 

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack  

~~~PH5 - LN5 - RID / ESS inspection Friday, April 18th / complete

04 stack - RID / ESS FINAL INSPECTION COMPLETED FRIDAY, MAY 1st.

~~~PH4 shutter installation complete

~~~1204 shutter installation complete

~~~1104/03 tile replacement 70 % complete

~~~1004 shutter installation complete / tile delivered for repair in center of balcony

~~~904 shutter installation complete

~~~804 shutter installation complete

~~~704 shutter installation complete / tile replacement 95% complete

~~~604 shutter installation complete

~~~504 shutter installation complete

~~~404 shutter installation complete 

~~~304 shutter installation complete

~~~LN4 shutter installation  complete

03 stack 

~~~PH3 shutter installation complete

~~~1203 shutter installation 95% complete

~~~LN3 shutter installation complete

~~~LN - 1003 / 1203 - PH old shutters removed / new shutters placed

02 stack - old shutter removal / new shutter placement DELAYED / JB using stage 

~~~PH2 - 402 inclusive;  JB stucco scraped & patched

~~~PH2 & 1202 painted

~~~PH - LN caulking inspection of every balcony complete April 24th

~~~702 tile trough repair started (waterproof membrane down) May 1st; fill in / leveling the week of, May 4th. 

 

Building #2:

06 stack

~~~SLC FINAL INSPECTIONS - several complete

05 stack - RID / ESS FINAL INSPECTION COMPLETED WEDNESDAY, April 29th.

~~~PH5 shutter installation complete

~~~1205 tile replacement 99% complete as of 4PM / shutter installation scheduled for week of May 4th

~~~1105 shutter installation complete

~~~1005 shutter installation complete

~~~905 shutter installation complete

~~~805 shutter installation complete

~~~705 shutter installation complete

~~~605 shutter installation complete

~~~505 shutter installation complete

~~~405 shutter installation complete

~~~305 shutter installation complete

~~~LN5 shutter installation  complete

04 stack - RID / ESS FINAL INSPECTION COMPLETED WEDNESDAY, April 29th.

~~~PH4 shutter installation complete

~~~1204 shutter installation complete

~~~1104 shutter installation  complete

~~~1004 shutter installation complete

~~~904 shutter installation complete

~~~804 shutter installation complete

~~~704 shutter installation complete 

~~~604 shutter installation complete

~~~504 shutter installation  complete

~~~404 shutter installation complete

~~~304 shutter installation  complete

~~~LN4 shutter installation complete

03 stack

~~~PH3 shutter installation complete

~~~1203 shutter installation complete

~~~1103 shutter installation complete

~~~LN3 shutter installation complete

02 stack

~~~LN2 take down completed

~~~302 take down completed / tile repair needed

~~~402 take down complete

~~~502 take down complete

~~~602 take down complete

~~~702 take down complete

~~~802 take down complete

~~~902 take down complete

~~~1002 take down complete

~~~1102 take down complete

~~~1202 take down 50% complete

 

PVC has been placed into all 01, 02, 03, 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project. 

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic