Shutter Update # 50

May 12, 2015

BUILDING 2

NORTH GROUND LEVEL EXIT / ENTRANCE AREA

FOR YOUR PROTECTION, A COVERED WALKWAY IS BEING ERECTED TUESDAY, MAY 12TH & WEDNESDAY, MAY 13TH at the NORTHWEST CORNER of each BUILDING.  BUILDING 1 90% COMPLETE MAY 12TH.

 

This will allow for SAFE PASSAGE through each building's NORTH GROUND LEVEL EXIT.  This is the same type walkway set up during JB's waterproofing project. 

 

 

BUILDING #1 

CROSSOVER TO THE POOL IS CLOSED from 8:AM to 4:30PM, Monday - Friday  due to construction starting on the 01 STACK.  PLEASE USE THE GROUND LEVEL EXIT WHEN GOING TO THE BEACH OR POOL AREA DURING THIS TIME. 

 

PLEASE DO NOT PLACE ITEMS ONTO YOUR EAST SIDE BALCONY IF YOU HAVE NOT RECEIVED A NOTICE THAT IT IS SAFE TO DO SO. 

 

RID / ESS FINAL INSPECTION    

ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

   

SLC FINAL INSPECTIONS / SIGN OFF - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time.   If you are in residence, you will be notified when the inspector and Regency Staff will inspect your shutters. 

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.  Old shutters will be removed from each balcony when new shutters are placed for installation.

 

PLEASE DIRECT ALL PROJECT RELATED QUESTIONS TO THE MANAGEMENT OFFICE OR CALL PAT'S CELL PHONE 772-201-1466

 

Building #1:

06 stack - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 06

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack  

~~~PH5 - LN5  ready for SLC to sign off

04 stack 

~~~RID / ESS final inspection completed May 1st

~~~PH4 shutter installation complete

~~~1204 shutter installation complete

~~~1104/03 shutter installation 40% complete

~~~1004 shutter installation complete / tile work complete

~~~904 shutter installation complete

~~~804 shutter installation complete

~~~704 shutter installation complete / tile replacement & painting complete

~~~604 shutter installation complete

~~~504 shutter installation complete

~~~404 shutter installation complete 

~~~304 shutter installation complete

~~~LN4 shutter installation 

03 stack 

~~~PH3 shutter installation complete

~~~1203 shutter installation complete

~~~1103/04 shutter installation 40% complete

~~~1003 shutter installation complete

~~~903 shutter installation complete

~~~803 shutter installation complete

~~~703 shutter installation complete

~~~603 shutter installation complete

~~~503 shutter installation complete

~~~403 shutter installation  complete

~~~303 shutter installation complete

~~~LN3 shutter installation complete

02 stack 

~~~502 shutter installation 95% complete

~~~402 shutter installation complete

~~~302 shutter installation complete

~~~LN2 shutter installation complete 

01 stack - caulking inspection Wednesday May 13th

~~~LN shutter take down complete

~~~301 shutter take down complete

~~~401 shutter take down complete

~~~501 shutter take down complete

~~~601 shutter take down complete

~~~701 shutter take down complete

~~~801 shutter take down complete

~~~901 shutter take down complete

~~~1001 shutter take down complete

~~~1101 shutter take down complete

~~~1201 shutter take down complete

~~~PH1 shutter take down complete

 

Building #2:

06 stack 

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack -

~~~RID / ESS final inspection completed April 29th.

~~~PH5 shutter installation complete

~~~1205 shutter installation complete / all tile & balcony paint work complete / edge work needed where new tile meets slab when staging is relocated

~~~1105 shutter installation complete

~~~1005 shutter installation complete

~~~905 shutter installation complete

~~~805 shutter installation complete

~~~705 shutter installation complete

~~~605 shutter installation complete

~~~505 shutter installation complete

~~~405 shutter installation complete

~~~305 shutter installation complete

~~~LN5 shutter installation  complete

04 stack 

~~~ready for SLC sign off

03 stack 

RID / ESS FINAL INSPECTION MAY 11TH

~~~PH3 shutter installation complete

~~~1203 shutter installation complete

~~~1103 shutter installation complete

~~~1003 shutter installation complete

~~~903 shutter installation complete

~~~803 shutter installation complete

~~~703 shutter installation complete

~~~603 shutter installation complete

~~~503 shutter installation complete

~~~403 shutter installation complete

~~~303 shutter installation complete

~~~LN3 shutter installation complete

02 stack 

~~~PH2 JB scrape, patch & paint

~~~1202 JB scrape, patch & paint

~~~1102 JB scrape, patch & paint

~~~1002 JB scrape, patch & paint

~~~902 JB scrape, patch & paint

~~~802 JB scrape, patch & paint

~~~PH - LN pressure washing complete

~~~Caulking inspection completed May 7th

01 stack - RID caulking inspection Wednesday May 13th

~~~LN1 take down complete

~~~301 take down complete

~~~401 take down complete

~~~501 take down complete

~~~601 take down complete

~~~701 take down complete

~~~801 take down complete

~~~901 take down complete

~~~1001 take down complete

~~~1101 take down complete

~~~1201 take down complete

~~~PH1 take down complete

 

PVC has been placed into all 01, 02, 03, 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project. 

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

BUILDING 2

NORTH GROUND LEVEL EXIT / ENTRANCE AREA

FOR YOUR PROTECTION, A COVERED WALKWAY IS BEING ERECTED TUESDAY, MAY 12TH & WEDNESDAY, MAY 13TH at the NORTHWEST CORNER of each BUILDING.  BUILDING 1 90% COMPLETE MAY 12TH.

 

This will allow for SAFE PASSAGE through each building's NORTH GROUND LEVEL EXIT.  This is the same type walkway set up during JB's waterproofing project. 

 

 

BUILDING #1 

CROSSOVER TO THE POOL IS CLOSED from 8:AM to 4:30PM, Monday - Friday  due to construction starting on the 01 STACK.  PLEASE USE THE GROUND LEVEL EXIT WHEN GOING TO THE BEACH OR POOL AREA DURING THIS TIME. 

 

PLEASE DO NOT PLACE ITEMS ONTO YOUR EAST SIDE BALCONY IF YOU HAVE NOT RECEIVED A NOTICE THAT IT IS SAFE TO DO SO. 

 

RID / ESS FINAL INSPECTION    

ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

   

SLC FINAL INSPECTIONS / SIGN OFF - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time.   If you are in residence, you will be notified when the inspector and Regency Staff will inspect your shutters. 

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.  Old shutters will be removed from each balcony when new shutters are placed for installation.

 

PLEASE DIRECT ALL PROJECT RELATED QUESTIONS TO THE MANAGEMENT OFFICE OR CALL PAT'S CELL PHONE 772-201-1466

 

Building #1:

06 stack - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 06

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack  

~~~PH5 - LN5  ready for SLC to sign off

04 stack 

~~~RID / ESS final inspection completed May 1st

~~~PH4 shutter installation complete

~~~1204 shutter installation complete

~~~1104/03 shutter installation 40% complete

~~~1004 shutter installation complete / tile work complete

~~~904 shutter installation complete

~~~804 shutter installation complete

~~~704 shutter installation complete / tile replacement & painting complete

~~~604 shutter installation complete

~~~504 shutter installation complete

~~~404 shutter installation complete 

~~~304 shutter installation complete

~~~LN4 shutter installation 

03 stack 

~~~PH3 shutter installation complete

~~~1203 shutter installation complete

~~~1103/04 shutter installation 40% complete

~~~1003 shutter installation complete

~~~903 shutter installation complete

~~~803 shutter installation complete

~~~703 shutter installation complete

~~~603 shutter installation complete

~~~503 shutter installation complete

~~~403 shutter installation  complete

~~~303 shutter installation complete

~~~LN3 shutter installation complete

02 stack 

~~~502 shutter installation 95% complete

~~~402 shutter installation complete

~~~302 shutter installation complete

~~~LN2 shutter installation complete 

01 stack - caulking inspection Wednesday May 13th

~~~LN shutter take down complete

~~~301 shutter take down complete

~~~401 shutter take down complete

~~~501 shutter take down complete

~~~601 shutter take down complete

~~~701 shutter take down complete

~~~801 shutter take down complete

~~~901 shutter take down complete

~~~1001 shutter take down complete

~~~1101 shutter take down complete

~~~1201 shutter take down complete

~~~PH1 shutter take down complete

 

Building #2:

06 stack 

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack -

~~~RID / ESS final inspection completed April 29th.

~~~PH5 shutter installation complete

~~~1205 shutter installation complete / all tile & balcony paint work complete / edge work needed where new tile meets slab when staging is relocated

~~~1105 shutter installation complete

~~~1005 shutter installation complete

~~~905 shutter installation complete

~~~805 shutter installation complete

~~~705 shutter installation complete

~~~605 shutter installation complete

~~~505 shutter installation complete

~~~405 shutter installation complete

~~~305 shutter installation complete

~~~LN5 shutter installation  complete

04 stack 

~~~ready for SLC sign off

03 stack 

RID / ESS FINAL INSPECTION MAY 11TH

~~~PH3 shutter installation complete

~~~1203 shutter installation complete

~~~1103 shutter installation complete

~~~1003 shutter installation complete

~~~903 shutter installation complete

~~~803 shutter installation complete

~~~703 shutter installation complete

~~~603 shutter installation complete

~~~503 shutter installation complete

~~~403 shutter installation complete

~~~303 shutter installation complete

~~~LN3 shutter installation complete

02 stack 

~~~PH2 JB scrape, patch & paint

~~~1202 JB scrape, patch & paint

~~~1102 JB scrape, patch & paint

~~~1002 JB scrape, patch & paint

~~~902 JB scrape, patch & paint

~~~802 JB scrape, patch & paint

~~~PH - LN pressure washing complete

~~~Caulking inspection completed May 7th

01 stack - RID caulking inspection Wednesday May 13th

~~~LN1 take down complete

~~~301 take down complete

~~~401 take down complete

~~~501 take down complete

~~~601 take down complete

~~~701 take down complete

~~~801 take down complete

~~~901 take down complete

~~~1001 take down complete

~~~1101 take down complete

~~~1201 take down complete

~~~PH1 take down complete

 

PVC has been placed into all 01, 02, 03, 04, 05 and 06 slider tracks to remind guests, realtors, and even residents, not to use the east side balcony. 

 

NOTE CHANGE:  Walt is assigned to Building #1 and Dave is assigned to Building #2 to check areas for security, cleanliness, and safety daily, throughout the project. 

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic