Shutter Update # 52

May 14, 2015

Building #1:

06 stack - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 06

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack  - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 05

~~~PH5 - LN5  ready for SLC to sign off

04 stack  - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 04

~~~PH4 - LN4  ready for SLC to sign off

03 stack - RID / ESS Final Inspection Monday, May 18th

~~~PH3 shutter installation complete

~~~1203 shutter installation complete

~~~1103 shutter installation complete

~~~1003 shutter installation complete

~~~903 shutter installation complete

~~~803 shutter installation complete

~~~703 shutter installation complete

~~~603 shutter installation complete

~~~503 shutter installation complete

~~~403 shutter installation  complete

~~~303 shutter installation complete

~~~LN3 shutter installation complete

02 stack 

~~~902 shutter installation started

~~~802 shutter installation complete

~~~702 shutter installation complete

~~~602 shutter installation complete

~~~502 shutter installation complete

~~~402 shutter installation complete

~~~302 shutter installation complete

~~~LN2 shutter installation complete 

01 stack - east balcony

~~~caulking inspection Monday, May 18th

~~~LN shutter take down complete

~~~301 shutter take down complete

~~~401 shutter take down complete

~~~501 shutter take down complete

~~~601 shutter take down complete

~~~701 shutter take down complete

~~~801 shutter take down complete

~~~901 shutter take down complete

~~~1001 shutter take down complete

~~~1101 shutter take down complete

~~~1201 shutter take down complete

~~~PH1 shutter take down complete

01 stack - kitchen balcony

~~~401 shutter take down 95% complete

~~~301 shutter take down complete 

~~~LN1 shutter take down complete

01 stack riverside balcony

~~~401 shutter take down 95% complete

~~~301 shutter take down complete

~~~LN1 shutter take down complete

01 stack k-bay window

~~~501 shutter take down 95% complete

~~~401 shutter take down complete

~~~301 shutter take down complete

~~~LN1 shutter take down complete

 

Building #2

06 stack 

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack

~~~PH5 - LN5  ready for SLC to sign off

~~~1205 edge work needed where new tile meets slab when staging is relocated

04 stack 

~~~PH4 - LN4 ready for SLC sign off

03 stack 

~~~RID / ESS Final Inspection May 11th

~~~PH3 shutter installation complete

~~~1203 shutter installation complete

~~~1103 shutter installation complete

~~~1003 shutter installation complete

~~~903 shutter installation complete

~~~803 shutter installation complete

~~~703 shutter installation complete

~~~603 shutter installation complete

~~~503 shutter installation complete

~~~403 shutter installation complete

~~~303 shutter installation complete

~~~LN3 shutter installation complete

02 stack 

~~~PH2 JB scrape, patch & paint

~~~1202 JB scrape, patch & paint

~~~1102 JB scrape, patch & paint

~~~1002 JB scrape, patch & paint

~~~902 JB scrape, patch & paint

~~~802 JB scrape, patch & paint

~~~PH - LN pressure washing complete

~~~Caulking inspection completed May 7th

01 stack - east balcony

~~~RID caulking inspection completed Wednesday May 13th

~~~LN1 - PH1 pressure washing complete

~~~PH1 stucco & patch

~~~1201 stucco & patch

~~~1101 stucco & patch

~~~1001 stucco & patch

~~~901 tile replacement starting Friday, May 15th

~~~801 stucco & patch

~~~701 stucco & patch

~~~601 stucco & patch

~~~501 stucco & patch

~~~401 stucco & patch

~~~301 stucco & patch

~~~LN1 stucco & patch

 

FOR YOUR PROTECTION, A COVERED WALKWAY HAS BEEN ERECTED at the NORTHWEST CORNER of each BUILDING.   

This will allow for SAFE PASSAGE through each building's NORTH GROUND LEVEL EXIT.

 

BUILDING #1 

CROSSOVER TO THE POOL MAY BE CLOSED from 8:AM to 4:30PM, Monday - Friday.  Construction has started on the 01 STACK.  PLEASE USE THE GROUND LEVEL EXIT WHEN GOING TO THE BEACH OR POOL AREA DURING THIS TIME. 

 

PLEASE DO NOT PLACE ITEMS ONTO YOUR EAST SIDE BALCONY IF YOU HAVE NOT RECEIVED A NOTICE THAT IT IS SAFE TO DO SO. 

 

RID / ESS FINAL INSPECTION    

ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

   

SLC FINAL INSPECTIONS / SIGN OFF - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time.   If you are in residence, you will be notified when the inspector and Regency Staff will inspect your shutters. 

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.  Old shutters will be removed from each balcony when new shutters are placed for installation.

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic