Shutter Update # 55

May 19, 2015

Dear Regency Residents,

 

In order for Expert Shutters' crew to access the riverside balcony area for shutter removal & installation, it is necessary to temporarily have a stage on the north and south end of the parking deck. 

 

The project is coming together and once completed there will be information which you will receive regarding the new shutter system.

 

BUILDING #1, 03 STACK -  Staging, has been moved to your west side balcony.  Please remove items from the west side and place them onto the east side balcony.  

 

BUILDING #1 

CROSSOVER TO THE POOL WILL BE CLOSED from 8:AM to 4:30PM, Monday - Friday.  Construction will begin again on the 01 EAST STACK.  PLEASE USE THE GROUND LEVEL EXIT WHEN GOING TO THE BEACH OR POOL AREA DURING THIS TIME. 

 

If you have any shutter project related questions or concerns, please email or phone the Management Office, or call my cell phone 772-201-1466.  If you have any questions regarding your specific unit, please don't hesitate to call me anytime.  Sincerely,  Pat

 

Building #1:

06 stack - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 06

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack  - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 05

~~~PH5 - LN5 SLC sign off 50% complete

04 stack  - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 04

~~~PH4 - LN4  ready for SLC to sign off

03 stack - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #1, stack 03

~~~PH3 - LN3 ready for SLC to sign off

02 stack 

~~~PH2 shutter installation 95% complete

~~~1202 shutter installation complete

~~~1102 scheduled with 1101

~~~1002 shutter installation complete

~~~902 shutter installation 95% complete

~~~802 shutter installation complete

~~~702 shutter installation complete

~~~602 shutter installation complete

~~~502 shutter installation complete

~~~402 shutter installation complete

~~~302 shutter installation complete

~~~LN2 shutter installation complete 

01 stack - east balcony

~~~caulking inspection completed Monday, May 18th

~~~PH - LN shutter take down complete / pressure washing complete

~~~PH stucco scraped & patched

~~~1201 stucco scraped & patched

01 stack - kitchen balcony

~~~901 shutter take down 95% complete

~~~801 shutter take down complete

~~~701 shutter take down complete

~~~601 shutter take down complete

~~~501 shutter take down complete

~~~401 shutter take down complete

~~~301 shutter take down complete 

~~~LN1 shutter take down complete

01 stack - k-bay window

~~~PH1 shutter take down complete

~~~1201 shutter take down complete

~~~1101 shutter take down complete

~~~1001 shutter take down complete

~~~901 shutter take down complete

~~~801 shutter take down complete

~~~701 shutter take down complete

~~~601 shutter take down complete

~~~501 shutter take down complete

~~~401 shutter take down complete

~~~301 shutter take down complete

~~~LN1 shutter take down complete

01 stack - riverside balcony

~~~1101 shutter take down complete

~~~1001 shutter take down complete

~~~901 shutter take down complete

~~~801 shutter take down complete

~~~701 shutter take down complete

~~~601 shutter take down complete

~~~501 shutter take down complete

~~~401 shutter take down complete

~~~301 shutter take down complete

~~~LN1 shutter take down complete

 

Building #2

06 stack - CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~furniture & other misc items can safely be returned to the east side balcony in Bldg #2, stack 06

~~~SLC FINAL INSPECTIONS - mostly complete

05 stack - waiting for stage to be relocated for 1205 balcony edge work

~~~PH5 - LN5  ready for SLC to sign off

~~~1205 edge work needed where new tile meets slab when staging is relocated week of May 18th - rescheduled for the end of the week

04 stack 

~~~PH4 - LN4 ready for SLC sign off

03 stack east balcony 

items need to be removed from the west balcony to the east balcony

~~~PH3 - LN3 ready for SLC to sign off

~~~RID / ESS Final Inspection May 11th

03 stack west balcony

02 stack 

~~~PH2 JB scrape, patch & paint

~~~1202 JB scrape, patch & paint

~~~1102 JB scrape, patch & paint

~~~1002 JB scrape, patch & paint

~~~902 JB scrape, patch & paint

~~~802 JB scrape, patch & paint

~~~702 JB scrape, patch & stucco work

~~~602 JB scrape, patch & stucco work

~~~502 JB scrape, patch & stucco work / placed new shutters & removed old shutters

~~~402 JB scrape, patch & stucco work / placed new shutters & removed old shutters

~~~302 JB scrape, patch & stucco work / pending tile repair

~~~LN2 JB scrape, patch & stucco work / placed new shutters / removed old shutters

01 stack - east balcony

~~~LN1 - PH1 pressure washing complete

~~~PH1 stucco & patch / painting complete

~~~1201 tile investigation (try for repair)  / stucco & patch / painting complete

~~~1101 stucco & patch / painting complete

~~~1001 stucco & patch / painting complete

~~~901 tile replacement (waterproofing membrane compl)

~~~801 stucco & patch / painting complete

~~~701 stucco & patch / painting complete

~~~601 stucco & patch / painting complete

~~~501 stucco & patch / painting complete

~~~401 stucco & patch / painting complete

~~~301 stucco & patch / painting complete

~~~LN1 stucco & patch / painting complete

01 stack kitchen balcony

01 stack k-bay window

01 stack riverside balcony

 

FOR YOUR PROTECTION, A COVERED WALKWAY HAS BEEN ERECTED at the NORTHWEST CORNER of each BUILDING.   

This will allow for SAFE PASSAGE through each building's NORTH GROUND LEVEL EXIT.

 

PLEASE DO NOT PLACE ITEMS ONTO YOUR EAST SIDE BALCONY IF YOU HAVE NOT RECEIVED A NOTICE THAT IT IS SAFE TO DO SO. 

 

RID / ESS FINAL INSPECTION    

ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

   

SLC FINAL INSPECTIONS / SIGN OFF - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time.   If you are in residence, you will be notified when the inspector and Regency Staff will inspect your shutters. 

 

Definitions 

Taken down:  This means when shutter blades & tracks are no longer installed on your balcony.

Removed:  This means when old shutters are taken off of your balcony.  Old shutters will be removed from each balcony when new shutters are placed for installation.

 

If you notice anything which warrants attention after hours, please call Security ASAP. 

 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic