Shutter Update #68

June 9, 2015

Dear Regency Residents,

 

SLC FINAL INSPECTION / SIGN OFF - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time. If you are in residence, you will be notified by phone, when the county inspector will be on-site to inspect your shutters for Final Sign-Off.

 

BUILDING #1 & #2, UNITS 03 & 04 WEST BATHROOM SHUTTERS - The shutters for this window are being reconfigured so both sides close from the outside. 

 

If you have any shutter project related questions or concerns, please email or phone the Management Office, or call my cell phone 772-201-1466.  If you have any questions regarding your specific unit, please don't hesitate to call me anytime.  Sincerely,  Pat

 

Building #1

06 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~SLC FINAL INSPECTIONS - mostly complete

06 stack kitchen balcony

06 stack k-bay window

06 stack riverside balcony

 

S Tower Elevator Lobby Window

 

05 stack   

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH5 - LN5 SLC sign off 50% complete

 

04 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH4 - LN4  SLC  50% signed off

04 stack west balcony

~~~PH - 304 pressure washing completed today, 6.9.2015

~~~PH4 - 304 completed caulking inspection  Thursday, 6.04.2015

04 stack west bath window

~~~PH - 304  completed caulking inspection  Thursday, 6.04.2015

 

03 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH3 - LN3 ready for SLC to sign off

03 stack west balcony 

~~~PH - 303 pressure washing completed today, 6.9.2015

~~~PH3 - 303 completed caulking inspection Thursday, 6.04.2015

03 stack west bath window

~~~PH - 303  completed caulking inspection  Thursday, 6.04.2015

 

02 stack 

~~~ESS & RID FINAL Inspection, May 21st

~~~PH2 shutter installation complete

~~~1202 shutter installation complete

~~~1102 with 01 - shutter installation 60% complete

~~~1002 shutter installation complete

~~~902 shutter installation complete

~~~802 shutter installation complete

~~~702 shutter installation complete

~~~602 shutter installation complete

~~~502 shutter installation complete

~~~402 shutter installation complete

~~~302 shutter installation complete

~~~LN2 shutter installation complete 

 

N Tower Elevator Lobby Window

~~~PH - ML  before pressure washing, JB caulked all stucco & open joints revealed when shutter tracks were removed.  Same scope of work as B1 K-bay windows.

~~~PH - ML  completed inspection of caulked shutter holes Thursday, 6.04.2015

 

01 stack - east balcony

~~~801 - PH1 removed old shutters / placed new

~~~PH1 stucco scraped & patched / paint complete

~~~1201 stucco scraped & patched / paint complete

~~~1101 shutter installation 60% complete

~~~1001 shutter installation complete

~~~901 shutter installation complete

~~~801 shutter installation complete

~~~701 shutter installation complete

~~~601 shutter installation complete

~~~501 shutter installation complete

~~~401 shutter installation complete

~~~301 shutter installation complete

~~~LN1 shutter installation complete

01 stack - kitchen balcony

~~~PH1 - LN1 caulking, pressure washing & painting complete

~~~PH1 - LN1 waterproofing / sealant inspection completed Friday, May 29th 

01 stack - k-bay window

~~~PH1 - LN1 caulking, pressure washing & painting complete

~~~PH1 - LN1 waterproofing / sealant inspection completed Friday, May 29th 

01 stack - riverside balcony

~~~PH1 - LN1 scraped, patch, stucco work & paint complete

 

Building #2

06 stack east 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~SLC FINAL INSPECTIONS - mostly complete / 1 pending

06 stack riverside balcony - rig scaffold / awaiting new date

06 stack k-bay window

06 stack kitchen balcony

 

S Tower Elevator Lobby Window

 

05 stack 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~SLC FINAL INSPECTIONS PH5 - LN5  sign off 100%

 

04 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH4 - LN4 ready for SLC sign off

04 stack west balcony

~~~304 take down complete

~~~404 take down complete

~~~504 take down complete

~~~704 take down 60% complete

04 stack west bath window 

~~~304 take down complete

~~~404 take down complete

~~~504 take down complete

 

03 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH3 - LN3 ready for SLC to sign off

03 stack west balcony

~~~303 take down complete

~~~403 take down complete

~~~503 take down complete

~~~704 take down 60% complete

03 stack west bath window

~~~303 take down complete

~~~403 take down complete

~~~503 take down complete

 

02 stack 

~~~Final Inspection complete other than 602

~~~PH2 shutter installation complete

~~~1202 shutter installation complete

~~~1102 shutter installation complete

~~~1002 shutter installation complete

~~~902 shutter installation complete

~~~802  shutter installation complete

~~~702  shutter installation complete

~~~602 tile rpr complete / JB balcony edge complete / ready for shutters

~~~502 shutter installation complete

~~~402 shutter installation complete

~~~302 shutter installation complete / JB balcony edge complete

~~~LN2 shutter installation complete

 

N tower elevator lobby window - rig scaffold / awaiting new date

 

01 stack - east balcony

~~~PH1 remove old / place new

~~~1201 tile grouting complete / detail finishing & east side edge work 6.10

~~~1101 shutter installation 20% complete

~~~1001 shutter installation complete

~~~901 shutter installation complete / detail finishing & east side edge work 6.10

~~~801 shutter installation complete

~~~701 shutter installation complete

~~~601 shutter installation complete

~~~501 shutter installation complete

~~~401 shutter installation complete

~~~301 shutter installation complete

~~~LN1 shutter installation complete

01 stack kitchen balcony 

~~~caulking inspection complete 6.1

~~~PH1 - LN1 caulking, stucco patch, & painting complete

~~~901 caulking, stucco patch, & painting complete / tile rpl

01 stack k-bay window

~~~caulking inspection complete 6.1

~~~PH1 - LN1 pressure washing complete

~~~PH1 - LN1 caulking, stucco patch, & painting complete

01 stack riverside balcony

~~~LN1 take down complete

~~~301 take down complete

~~~401 take down complete

~~~501 take down complete

~~~601 take down complete

~~~701 take down complete

~~~801 take down complete

~~~901 take down complete

~~~1001 take down complete

~~~1101 take down complete

 

In order for Expert Shutters' crew to access the 01 stack west balcony area for shutter removal & installation, it is necessary to temporarily have a stage on the north end of the parking deck.  As installation progresses, the stage will be relocated to the south end of the parking deck to access the elevator lobby window & the 06 west balconies. 

 

FOR YOUR PROTECTION, A COVERED WALKWAY HAS BEEN ERECTED at the NORTHWEST CORNER of each BUILDING.    This will allow for SAFE PASSAGE through each building's NORTH GROUND LEVEL EXIT.

 

RID / ESS FINAL INSPECTION    

ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

   

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic