Shutter Update #73

June 17, 2015

Dear Regency Residents,

 

Beginning tomorrow, June 18th, through the duration of the project, Expert Shutters will begin work at 7:AM - 3:PM. 

 

SLC FINAL INSPECTION / SIGN OFF - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time. If you are in residence, you will be notified by phone, when the county inspector will be on-site to inspect your shutters for Final Sign-Off.

BLDG #2 03 STACK is scheduled for Sign-off Thursday, June 18th

 

If you have any shutter project related questions or concerns, please email or phone the Management Office, or call my cell phone 772-201-1466.  If you have any questions regarding your specific unit, please don't hesitate to call me anytime.  Sincerely,  Pat

 

Building #1

06 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH6 - LN6 SLC sign off complete

06 stack kitchen balcony

06 stack k-bay window

06 stack riverside balcony

 

S Tower Elevator Lobby Window

 

05 stack   

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH5 - LN5 SLC sign off complete

 

04 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH4 - LN4  SLC  sign off complete

04 stack west balcony

~~~PH4 - 304 scraped, caulked, patched & painted 

04 stack west bath window

~~~PH4 - 304  scraped, caulked, patched & painted 

 

 

03 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH3 - LN3 SLC sign off complete

03 stack west balcony 

~~~PH3 - 303 scraped, caulked, patched & painted 

~~~903  scraped, caulked & patched / paint 6.16

03 stack west bath window

~~~PH3  scraped, caulked, patched & painted 

~~~903  scraped, caulked & patched / paint 6.16

 

02 stack 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~ESS & RID FINAL Inspection, May 21st

~~~PH2 - LN2 ready for SLC to sign off

 

N Tower Elevator Lobby Window

~~~PH - ML painting complete - RID inspection Wednesday, June 17th

~~~PH - ML  before pressure washing, JB caulked all stucco & open joints revealed when shutter tracks were removed.  Same scope of work as B1 K-bay windows.

~~~PH - ML  completed inspection of caulked shutter holes Thursday, 6.04.2015

 

01 stack - east balcony

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~ESS & RID Final Inspection completed Friday, June 12th

~~~PH1 - LN1 ready for SLC to sign off 

01 stack - kitchen balcony

~~~901 shutter installation 20% complete

~~~801 shutter installation complete

~~~701 shutter installation complete

~~~601 shutter installation complete

~~~501 shutter installation complete

~~~401 shutter installation complete

~~~301 shutter installation complete

~~~LN1 shutter installation complete

01 stack - k-bay window

~~~PH1 - LN1 caulking, pressure washing & painting complete

~~~PH1 - LN1 waterproofing / sealant inspection completed Friday, May 29th 

01 stack - riverside balcony

~~~PH1 shutter installation complete

~~~1201 shutter installation complete

~~~1101 shutter installation 60% complete / not bathroom window

~~~1001 shutter installation 60% complete / not bathroom window

~~~901 shutter installation 60% complete / not bathroom window

~~~801 shutter installation 60% complete / not bathroom window

~~~701 shutter installation 20% complete / not bathroom window

~~~601 shutter installation 20% complete / not bathroom window

~~~501 shutter installation 50% complete / not bathroom window

~~~401 shutter installation 50% complete / not bathroom window

 

Building #2

06 stack east 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH6 - LN6  SLC FINAL INSPECTIONS - sign off complete

06 stack riverside balcony

06 stack k-bay window

06 stack kitchen balcony

 

S Tower Elevator Lobby Window

 

05 stack 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH5 - LN5  SLC FINAL INSPECTIONS - sign off complete

 

04 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH4 - 1004 & 804 - LN4  SLC sign off complete

~~~904  tile ordered for repair

04 stack west balcony / west bath window 

~~~RID Caulking Inspection Thursday, 6.18

~~~304 take down complete

~~~404 take down complete

~~~504 take down complete

~~~604 take down complete

~~~704 take down complete

~~~804 take down complete

~~~904 take down complete

~~~1004 take down complete

~~~1104 take down complete

~~~1204 take down complete

~~~PH4 take down complete

 

03 stack east balcony 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH3 - LN3 ready for SLC to sign off

03 stack west balcony / west bath window

~~~RID Caulk Inspection Thursday, 6.18

~~~303 take down complete

~~~403 take down complete

~~~503 take down complete

~~~603 take down complete

~~~703 take down complete

~~~803 take down complete

~~~903 take down complete

~~~1003 take down complete

~~~1103 take down complete

~~~1203 take down complete

~~~PH3 take down complete

 

02 stack 

CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY

~~~PH2 - LN2 shutter installation complete

 

N tower elevator lobby window   RID Caulk Inspection Thursday, 6.18

PH - LN take down complete

 

01 stack - east balcony

~~~PH1 - LN1 ready for SLC to sign off

~~~PH1 - LN1 shutter installation complete

~~~ESS & RID Final Inspection completed Friday AM, June 12th

01 stack kitchen balcony 

~~~caulking inspection complete 6.1

~~~PH1 - LN1 caulking, stucco patch, & painting complete

~~~901 caulking, stucco patch, & painting complete / tile rpl 6.18 & grout 6.19

01 stack k-bay window

~~~caulking inspection complete 6.1

~~~PH1 - LN1 pressure washing complete

~~~PH1 - LN1 caulking, stucco patch, & painting complete

01 stack riverside balcony

~~~PH1 pressure wash, clean & caulk & stucco work complete 

~~~1201 pressure wash, clean & caulk & stucco work complete

~~~PH1 - LN1 take down complete

 

BUILDING #1 & #2:

Furniture can be put back onto the east balconies all units.

Units 03 & 04 west bathroom window shutters are being reconfigured so both sides close from the outside. 

Units 01 & 06 kitchen bay window shutters are being reconfigured so the upper locking pin will be longer and easier to access when securing the shutters.   

 

In order for Expert Shutters' crew to access the 01 stack west balcony area for shutter removal & installation, it is necessary to temporarily have a stage on the north end of the parking deck.  As installation progresses, the stage will be relocated to the south end of the parking deck to access the elevator lobby window & the 06 west balconies. 

 

FOR YOUR PROTECTION, A COVERED WALKWAY HAS BEEN ERECTED at the NORTHWEST CORNER of each BUILDING.    This will allow for SAFE PASSAGE through each building's NORTH GROUND LEVEL EXIT.

 

RID / ESS FINAL INSPECTION    

ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

   

If you notice anything which warrants attention after hours, please call Security ASAP. 

vDear Regency Residents, Beginning tomorrow, June 18th, through the duration of the project, Expert Shutters will begin work at 7:AM - 3:PM. SLC FINAL INSPECTION / SIGN OFF - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time. If you are in residence, you will be notified by phone, when the county inspector will be on-site to inspect your shutters for Final Sign-Off. BLDG #2 03 STACK is scheduled for Sign-off Thursday, June 18th If you have any shutter project related questions or concerns, please email or phone the Management Office, or call my cell phone 772-201-1466. If you have any questions regarding your specific unit, please don't hesitate to call me anytime. Sincerely, Pat Building #1 06 stack east balcony CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY~~~PH6 - LN6 SLC sign off complete06 stack kitchen balcony06 stack k-bay window06 stack riverside balcony S Tower Elevator Lobby Window 05 stack CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY~~~PH5 - LN5 SLC sign off complete 04 stack east balcony CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY~~~PH4 - LN4 SLC sign off complete04 stack west balcony ~~~PH4 - 304 scraped, caulked, patched & painted 04 stack west bath window~~~PH4 - 304 scraped, caulked, patched & painted 03 stack east balcony CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY ~~~PH3 - LN3 SLC sign off complete03 stack west balcony ~~~PH3 - 303 scraped, caulked, patched & painted ~~~903 scraped, caulked & patched / paint 6.1603 stack west bath window~~~PH3 scraped, caulked, patched & painted ~~~903 scraped, caulked & patched / paint 6.16 02 stack CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY~~~ESS & RID FINAL Inspection, May 21st~~~PH2 - LN2 ready for SLC to sign off N Tower Elevator Lobby Window~~~PH - ML painting complete - RID inspection Wednesday, June 17th~~~PH - ML before pressure washing, JB caulked all stucco & open joints revealed when shutter tracks were removed. Same scope of work as B1 K-bay windows.~~~PH - ML completed inspection of caulked shutter holes Thursday, 6.04.2015 01 stack - east balcony CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY~~~ESS & RID Final Inspection completed Friday, June 12th~~~PH1 - LN1 ready for SLC to sign off 01 stack - kitchen balcony~~~901 shutter installation 20% complete~~~801 shutter installation complete~~~701 shutter installation complete~~~601 shutter installation complete~~~501 shutter installation complete~~~401 shutter installation complete~~~301 shutter installation complete~~~LN1 shutter installation complete01 stack - k-bay window ~~~PH1 - LN1 caulking, pressure washing & painting complete~~~PH1 - LN1 waterproofing / sealant inspection completed Friday, May 29th 01 stack - riverside balcony ~~~PH1 shutter installation complete~~~1201 shutter installation complete~~~1101 shutter installation 60% complete / not bathroom window~~~1001 shutter installation 60% complete / not bathroom window~~~901 shutter installation 60% complete / not bathroom window~~~801 shutter installation 60% complete / not bathroom window~~~701 shutter installation 20% complete / not bathroom window~~~601 shutter installation 20% complete / not bathroom window~~~501 shutter installation 50% complete / not bathroom window~~~401 shutter installation 50% complete / not bathroom window Building #206 stack east CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY ~~~PH6 - LN6 SLC FINAL INSPECTIONS - sign off complete06 stack riverside balcony 06 stack k-bay window06 stack kitchen balcony S Tower Elevator Lobby Window 05 stack CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY ~~~PH5 - LN5 SLC FINAL INSPECTIONS - sign off complete 04 stack east balcony CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY ~~~PH4 - 1004 & 804 - LN4 SLC sign off complete ~~~904 tile ordered for repair 04 stack west balcony / west bath window ~~~RID Caulking Inspection Thursday, 6.18~~~304 take down complete~~~404 take down complete~~~504 take down complete~~~604 take down complete~~~704 take down complete~~~804 take down complete~~~904 take down complete~~~1004 take down complete~~~1104 take down complete~~~1204 take down complete~~~PH4 take down complete 03 stack east balcony CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY ~~~PH3 - LN3 ready for SLC to sign off03 stack west balcony / west bath window ~~~RID Caulk Inspection Thursday, 6.18~~~303 take down complete~~~403 take down complete~~~503 take down complete~~~603 take down complete~~~703 take down complete~~~803 take down complete~~~903 take down complete~~~1003 take down complete~~~1103 take down complete~~~1203 take down complete~~~PH3 take down complete 02 stack CLEARED FOR FURNITURE & SAFE USE OF EAST BALCONY~~~PH2 - LN2 shutter installation complete N tower elevator lobby window RID Caulk Inspection Thursday, 6.18PH - LN take down complete 01 stack - east balcony ~~~PH1 - LN1 ready for SLC to sign off~~~PH1 - LN1 shutter installation complete~~~ESS & RID Final Inspection completed Friday AM, June 12th01 stack kitchen balcony ~~~caulking inspection complete 6.1~~~PH1 - LN1 caulking, stucco patch, & painting complete~~~901 caulking, stucco patch, & painting complete / tile rpl 6.18 & grout 6.1901 stack k-bay window~~~caulking inspection complete 6.1~~~PH1 - LN1 pressure washing complete~~~PH1 - LN1 caulking, stucco patch, & painting complete01 stack riverside balcony ~~~PH1 pressure wash, clean & caulk & stucco work complete ~~~1201 pressure wash, clean & caulk & stucco work complete~~~PH1 - LN1 take down complete BUILDING #1 & #2: Furniture can be put back onto the east balconies all units.Units 03 & 04 west bathroom window shutters are being reconfigured so both sides close from the outside. Units 01 & 06 kitchen bay window shutters are being reconfigured so the upper locking pin will be longer and easier to access when securing the shutters. In order for Expert Shutters' crew to access the 01 stack west balcony area for shutter removal & installation, it is necessary to temporarily have a stage on the north end of the parking deck. As installation progresses, the stage will be relocated to the south end of the parking deck to access the elevator lobby window & the 06 west balconies. FOR YOUR PROTECTION, A COVERED WALKWAY HAS BEEN ERECTED at the NORTHWEST CORNER of each BUILDING. This will allow for SAFE PASSAGE through each building's NORTH GROUND LEVEL EXIT. RID / ESS FINAL INSPECTION ESS & RID inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. If you notice anything which warrants attention after hours, please call Security ASAP.

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic