Shutter Update #81

June 26, 2015

Dear Regency Residents,

 

If you have items which need to be addressed on a punch list, please email the information to Pattp814@aol.com so your individual issue may be dealt with at this time.

 

SLC FINAL INSPECTION / SIGN OFF - the Final Inspection of each set of shutters by SLC is being coordinated per stack rather than several units at a time. If you are in residence, you will be notified by phone, when the county inspector will be on-site to inspect your shutters for Final Sign-Off. 

 

Due to extreme high heat, Expert Shutters will begin work between 7:AM - 3:PM for the duration of the project. 

 

NOTE: The west area shutter inspections for 01 & 06 -  St Lucie County sign-off will be coordinated when the kitchen balcony, kitchen bay window, and riverside balcony shutter installations are all completed.

 

If you have any shutter project related questions or concerns, please email or phone the Management Office, or call my cell phone 772-201-1466.  If you have any questions regarding your specific unit, please don't hesitate to call me anytime. 

 

Expert Shutters is removing all old shutters from west balcony areas beginning with the north end of Bldg #2 and working south.    Sincerely,  Pat

 

Building #1

06 stack east balcony 

~~~PH6 - LN6 SLC sign off complete

06 stack kitchen balcony

06 stack k-bay window

06 stack riverside balcony

~~~PH6 - LN6 caulking inspection June 24th

~~~PH6 take down complete

~~~1206 take down complete

~~~1106 take down complete

~~~1006 take down complete

~~~906 take down complete

~~~806 take down complete

~~~706 take down complete

~~~606 take down complete

~~~506 take down complete

~~~406 take down complete

~~~306 take down complete

~~~LN6 shutter installation complete

 

S Tower Elevator Lobby Window

 

05 stack   

~~~PH5 - LN5 SLC sign off complete

 

04 stack east balcony 

~~~PH4 - LN4  SLC  sign off complete

04 stack west balcony / bath window

~~~404 shutter installation 30% complete 

~~~304 shutter installation complete

~~~PH4 - 704 old shutters removed

~~~LN4 - 604 removed old / replaced new  

 

03 stack east balcony 

~~~PH3 - LN3 SLC sign off complete

03 stack west balcony / bath window

~~~403 shutter installation 30% complete

~~~303 shutter installation complete

~~~PH3 - 703 old shutters removed

~~~LN3 - 603 removed old / replaced new  

 

02 stack 

~~~PH2 - LN2 SLC sign off complete

 

N Tower Elevator Lobby Window

~~~PH - ML painting complete - RID inspection Wednesday, 6.17

~~~PH - ML  before pressure washing, JB caulked all stucco & open joints revealed when shutter tracks were removed.  Same scope of work as B1 K-bay windows.

 

01 stack - east balcony

~~~PH1 - LN1 ready for SLC to sign off 

~~~ESS & RID Final Inspection completed Friday, June 12th

01 stack - kitchen balcony

~~~PH1 - LN1 ready for SLC to sign off 

~~~PH1 - LN1 shutter installation complete

01 stack - k-bay window

~~~PH1 - LN1 caulking, pressure washing & painting complete 

01 stack - riverside balcony 

~~~punch list items complete for June 29th inspection

~~~PH1 - LN1  June 24 inspection 

 

Building #2

06 stack east  

~~~PH6 - LN6  SLC sign off complete

06 stack riverside balcony

~~~PH6 take down complete

~~~1206 take down complete

~~~1106 take down complete

~~~1006 take down complete

~~~906 take down complete

~~~806 take down complete

~~~706 take down complete

~~~606 take down complete

~~~506 take down complete

~~~406 take down complete

~~~306 take down complete

~~~LN6 take down complete

06 stack k-bay window

06 stack kitchen balcony

 

S Tower Elevator Lobby Window

 

05 stack 

~~~PH5 - LN5  SLC sign off complete

 

04 stack east balcony 

~~~PH4 -1004 & 804 - LN4  SLC sign off complete

~~~904  tile repair complete

04 stack west balcony / west bath window 

~~~PH4 - LN4 scrape, patch & stucco work complete

~~~PH4 painting complete

~~~1204 painting complete

~~~1104 painting complete

~~~1004 painting complete

~~~904 painting complete

~~~804 painting complete

~~~704 painting complete

~~~604 painting complete

~~~504 painting complete

~~~404 painting complete

~~~304 painting complete

 

03 stack east balcony  

~~~PH3 - LN3 SLC sign off complete

03 stack west balcony / west bath window

~~~PH3 - LN3 scrape, patch & stucco work complete

~~~PH3 painting complete

~~~1203 painting complete

~~~1103 painting complete

~~~1003 painting complete

~~~903 painting complete

~~~803 painting complete

~~~703  painting complete

~~~603 painting complete

~~~503 painting complete

~~~403 painting complete

~~~303 painting complete

 

02 stack 

~~~PH2 - LN2 SLC sign off complete

~~~PH2 - LN2 shutter installation complete

 

N tower elevator lobby window  

~~~PH - 5 scrape, patch & stucco work complete

~~~pressure washing complete

~~~PH - LN take down complete

~~~RID Caulking Inspection completed, Thursday, 6.18

 

01 stack - east balcony

~~~PH1 - LN1 ready for SLC to sign off

~~~ESS & RID Final Inspection completed Friday AM, June 12th

01 stack kitchen balcony 

~~~PH1 - LN1 shutter installation complete

~~~PH1 - LN1 caulking, stucco patch, & painting complete

01 stack k-bay window

~~~caulking inspection complete 6.1

~~~PH1 - LN1 caulking, stucco patch, & painting complete

01 stack riverside balcony

~~~PH1 - LN1 pressure wash, clean & caulk & stucco work complete 

~~~1201 shutter installation 60% complete

~~~1101 shutter installation 60% complete

~~~1001 shutter installation complete

~~~901 shutter installation complete

~~~801  shutter installation complete

~~~701 shutter installation complete

~~~601 shutter installation complete

~~~501 shutter installation complete

~~~401 shutter installation complete

~~~301 shutter installation complete

~~~LN1 shutter installation complete

 

 

BUILDING #1 & #2:

Furniture can be put back onto the east balconies all units.

Units 03 & 04 west bathroom window shutters are being reconfigured so both sides close from the outside. 

Units 01 & 06 kitchen bay window shutters are being reconfigured so the upper locking pin will be longer and easier to access when securing the shutters.   

 

In order for Expert Shutters' crew to access the 01 stack west balcony area for shutter removal & installation, it is necessary to temporarily have a stage on the north end of the parking deck.  As installation progresses, the stage will be relocated to the south end of the parking deck to access the elevator lobby window & the 06 west balconies. 

 

FOR YOUR PROTECTION, A COVERED WALKWAY HAS BEEN ERECTED at the NORTHWEST CORNER of each BUILDING.    This will allow for SAFE PASSAGE through each building's NORTH GROUND LEVEL EXIT.

 

RID / ESS FINAL INSPECTION    

ESS & RID installation inspections include closing, locking, and re-opening every set of shutters, in addition to checking caulking, fasteners, and cleanliness. 

   

If you notice anything which warrants attention after hours, please call Security ASAP. 

Please reload

Featured Posts

May 28, 2019 Island Dunes Country Club Announcement

2019 IDCC Schedule

May 28, 2019

1/2
Please reload

Recent Posts
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
Follow Us

I'm busy working on my blog posts. Watch this space!

Please reload

Search By Tags

May 20, 2020

January 6, 2020

Please reload

© 2014 by The-Regency.com Proudly created with Wix.com

  • Facebook Classic
  • Twitter Classic
  • YouTube Classic
  • Flickr Classic